OPERATION & MAINTENANCE OF GROUNDWATER REMEDIATION SYSTEM

Envirofix was retained by a client to provide Operation and Maintenance (O&M) services to a Groundwater Remediation System (GWRS) on former manufacturing plant in Burlington, Ontario.

Project description

Services: Operation and Maintenance of an existing Groundwater Remediation System 

Project Duration: 2007


The scope of work of EnviroFix consisted of the following:

Upon start of the project, EnviroFix removed and replaced all the malfunctioning components of the GWRS and conducted complete overhaul of the system.   

  • Remove and replaced or repaired filtration components of the system on as needed basis
  • Pump out the accumulated sludge In the collection sump on as needed basis
  • Recorded and documented the maintenance activity and submitted to the client’s consultant.